← All Projects

Industrial · Emergency Restoration

San Carlos Industrial Renovation

San Carlos, CA

150,000 SFMixed-Use Industrial
8+ MonthsTimeline Accelerated
MSBFull Switchgear Replacement
Multi-TenantZero Business Disruption

Overview

When the power went out, Keystone stepped in.

After an arc flash incident knocked out power at a 150,000 SF mixed-use industrial site in San Carlos, the multi-tenant property — integrated office and warehouse spaces — was running on costly temporary generators. Keystone stepped in to spearhead the re-energization and main switchboard replacement.

Collaborating closely with PG&E and McMillan Electric, Keystone orchestrated the project and accelerated the timeline by more than eight months — managing the safe installation of new switchgear, a concrete landing pad, and a submetering system. The property was meticulously restored, and every tenant kept their business running throughout.

Project Scope

Location: San Carlos, CA
Size: 150,000 SF mixed-use industrial
Type: Emergency Re-Energization / MSB Replacement
Partners: PG&E, McMillan Electric
Scope: New switchgear, concrete landing pad, submetering system
Result: Timeline expedited 8+ months, full business continuity